Location: Westminster, London
Contract Value: £350,000,000
Programme: 17 Weeks
The project required meticulous planning and execution across several critical phases.
Piling attendance marked the initial phase, where foundations were carefully laid to ensure stability and support for subsequent construction.
The construction of the basement followed, involving excavation and the installation of structural elements to expand usable space efficiently. Steelwork installation was pivotal in reinforcing the building’s framework, enabling structural alterations that aligned with modern architectural standards and design specifications.
These phases were executed with precision and adherence to safety protocols, laying the groundwork for the successful completion of the project.